Site icon Project Management 123

Concrete Pile Works and Load Testing Requirements

All materials to be used for the piling concrete works shall meet the requirements as specified under relevant specifications of a project, and any cement to be used for concrete piles shall be a suitable combination of GGBFS,  satisfying ASTM C989, CEM II to BS EN 197-1:200 or BS 4246-1996 & OPC type I to ASTM C150 or CEM I to BS EN 197-1 2000: or BS-12 and as approved and required by consultant / client.

The British Standards referred to in this Specification are listed below, together with any other references specified.  Any differences between their requirements and this Specification shall be submitted to the consultant for ruling.

Temporary Casing

Generally cast-in-situ (bored) piles with temporary casing method BS 2004 and BS 8004 will be permitted for execution. Installing bored cast in situ piles using CFA will not be permitted. Immediately after the drilling, the reinforcement has to be placed; ensuring a minimum concrete cover of 75 mm, and the pile has to be cast.

Drilling Operation

Pile Concreting

Pile Testing Requirements

Basics For Test Piles

The contractor shall carry out successful foundation load tests in order to prove the suitability of the pile foundation selected with particular type of soil.  The results of the tests shall be submitted in a format for approval by the ENGINEER. The contractor is requested to include his price for test piles and testing of piles in the erection price of his offer.

Piling Type Tests (Preliminary Pile Test)

Prior to piling commencement the contractor shall install one test pile of each type proposed. The piles shall be test loaded in conformity with the relevant Standards, e.g. ASTM D 1143, BS 8004, or DIN 1054.

The piles shall be considered as acceptable in case the obtained load-settlement/heave diagrams do not indicate movements beyond permissible limits as per the relevant Standards or written in this section. It is to the discretion of consultant to test any pile up to destruction.

Piling Foundation Routine Test (Working Pile Test)

In addition to the above tests the contractor shall perform routine tests at working foundations in order to guarantee the design requirements given in this Specification at 2% of the working piles, with minimum of 2 piles for each type.

The integrity of the piles shall be carried on 100% of piles.

Details for Pile Tests

Test Reports

Reports on pile testing shall be submitted to the ENGINEER and shall contain, among others, the following information:

–    Layout of test equipment and description.

–    Pile identification, diameter and length.

–    Sketch of soil conditions and ground water location.

–    Complete records of level, load cell and dial gauge readings against date and time throughout the test, preferably in tabulation form.

–    Graphs of load and settlement/heave versus time.

–    Graphs of settlement/heave versus load.

–    Remarks concerning any unusual occurrences during the loading of the pile.

Evaluation / Conclusion

An acceptable design load will be determined by consultant based on the results evaluations of the loading test of a pile.  Generally, a pile shall not have a total settlement of more than 1.5% of pile diameter or residual (net) settlement, after removal of the ultimate or maximum load, exceeding 6 mm, whichever is less. The pile not satisfying the above mentioned criterion will be considered insufficient to carry the required loads and will be treated as failure. A pile shall be considered satisfactory if it satisfies the entire criterion stated under relevant sections of BS 8004, in addition to the above mentioned criteria.

If the result of the test on the pile(s) is not to the satisfaction of consultant, the contractor shall change the system or the design of the piles,

and choose any type of piles approved by the consultant for which test piles will be constructed and the loading test performed until the contractor gets successful results without extra cost and without extension of time.

For working piles residual or net settlement shall not exceed 4.5mm, after removal of all loads.

Exit mobile version