Method Statement for Cable Laying and Termination for Control and Signal Cables

The purpose of this method statement is to provide general guidelines for cable laying and cable termination for control and signal cables.

Scope of this method statement covers the followings activities.

The following documents are considered as reference documents:

Mandatory Tools

Abbreviations 

SE: Site engineer

SUP: Supervisor

ITP: Inspection and test plan

E&I: Electrical and instrument

QA/QC: Quality assurance and control

MS: Method statement

IFC: Issue for construction

PPE: Personal protection equipment

HSE: Health safety & environment

PTW: Permit to work

Responsibilities

Supervisor will check cable routing as per project drawings and specifications, all cables, control and instrument to be laid and installed as per above standard details.

Site engineer is to ensure that all activities mentioned above comply with project drawings, specifications and standard details

PTW Holder: Work permit system will be followed. work-permit coordinator will be responsible for this and the work-permit holder will be responsible to follow work-permit requirements.

Method of Cable Laying Work

Receipt and storage of material

The material received from client shall be stored in designated area of store.
arrangements shall be made to protect against effects of weather and environment.

Arrangement cable laying for termination

Pre-installation requirements

Preparing for Cable Laying

Cable Laying Procedure

Cable drum is to be shifted to site and jacked up for laying out. the drum jacking arrangement is to be suitable for the size and weight of the drum.

Unrolling of the cable is as per direction shown on drum.

For large size cable, a proper size cable pulling sock shall be used.
sufficient no. of skilled & unskilled  workers are to be employed to lay the cable taking care of the following:-

Cable Termination Procedure

All jointing and termination work shall be carried out by trained technicians, experienced in such work for the operating voltage concerned.

Proper crimping tools shall be used for compression type lugs.

All cables are to be terminated used glands of proper type and size as per area classification.

The gland shall be assembled strictly in accordance with the manufacturer’s instruction, particular attention being paid to ensuring good mechanical and electrical contact between parts with out excessive strain or distortion of cable.

The entire body of the cable must enter the gland. the cable shall be on a straight axis from a point at least six diameter before entering the gland. seals shall be checked for correct size at the point of application.

Unused cable entries shall be closed with plug suitable for the degree of protection and classification.

Circuit Identification

Proper identification tags shall be used for identification of the cables. Cables cores shall be positively identified at every terminal point, in accordance with the drawings and specification.

Inspection

Inspection and test plan specific to project requirements shall be followed and inspections activities are recorded on the formats. .

Precautions

existing installations

new installations

Scaffolding

Safety Instructions

During the installation all measures shall be adopted to ensure safe working.