Method Statement For False Ceiling Works Gypsum Board, Beam Grid, Ceiling Tiles & Baffles

The following Method Statement describes the procedure and equipment required for the false ceiling works.

Below civil method statement covers following types of false ceilings:

Necessary Tools & Equipment

Following tools shall be arranged before the starting the works for false ceiling installation:

Installation Procedure for False Ceiling Works

GYPSUM AND CEMENT BOARD FALSE CEILING:

Handling and storage:

 Leveling & Fixing of Wall Angles:

Fixing of Suspension Grid:

Fixing of Gypsum Board:

Gypsum Board Vertical Bulkheads and Cove Light:

BEAM GRID SYSTEM FALSE CEILING

Durlum metal ceilings are usually delivered on pallets.

It is advisable to leave the metal panels on the pallets as long as possible.

If the pallets have to be opened, the durlum metal panels should always be positioned on the long side, it can then be placed carefully against the wall, do not store flat.

Storage must be carried out such a manner that there is no chance of damage.

The assembly of the ceiling panels must not start until all dust-producing work has been completed.

Mounting Sequence:

Assembly Sub Construction:

The general distance for mounting the perimeter trim is max. 500mm.

This general distance is less, depending on additional loads, the type of wall and special requirements.

Assembly of primary profile

Assembly of the ceiling panels:

BAFFLE FALSE CEILING

 Storage:

Mounting Sequences:

 Assembly Sequence:

Distance of the Suspension:

Distance of the AP primary profiles according to EN 13964:

Recommended every 1500mm as directly mounted suspension

Distance of the AS secondary profiles according to EN 13964:

Recommended at least every 1500mm with min 2 per baffle.

Distance of the AH suspension points:

Recommended every 1000mmas directly screwed to the primary profile U 1040.

 

INSTALLING CEILING TILES 600 x 600mm and 600 x 1200mm

Leveling and Fixing of Wall Angles:

Structural wall must be plastered or finished by any other finishes required by client.

Finished floor level marks must be available in all areas by using level instruments.

Points will be marked on walls by measuring the required ceiling level from the existing marks using measuring tape.

The maximum points spacing should be five meters, then a continuous line will be marked between the points by using chalk line.

All high level works including fire stopping, forming of penetrations to be completed.

Powder coated W-shape wall angles will be fixed on the marked lines to the structural wall or partition walls by using concrete rails or black Screws with plastic anchor of 25mm length and will be fixed at a spacing of 300m centre to centre.

Testing of hangers will be concluded as per specification & refer to field quality control requirements.

Location of access hatches to be allowed when installing hanging supports.

Fixing of Suspension Grid:

After receiving clearances from MEP Subcontractors, ceiling nails will be fixed to the ceiling structure by using shooting gun machines at spacing of 1200mm distributed according to ceiling tiles layout on the approved shop drawings.

Hooked steel rods of diameter 4mm will be inserted to the ceiling nails from one end.

The other end of the rods will be inserted in a steel adjustment clip.

Length of the rods will equal to the height of structural ceiling to the false ceiling less 200mm.

Another set of 4mm diameter steel rods will be inserted to the other end of each adjustment clip.

The length of these rods is 300mm in which they have hooked shape at the other end.

Installing of these hangers should be plumb & free from contact with insulation or other objects within ceiling plenum that are not part of supporting structure or of ceiling suspension system.

In case width of services (A/C ducts…) interfering with the location of hanger at required spacing, a bracing system will be provided around such services & then the hangers will be attached & suspended to the suspension system.

The hooked end of the rods will be hanged into the holes of the vertical flange of the main runner steel T-grid suspension with a minimum of four tight turning.

Length of the main runner is 3600mm in long span rooms.

The main runners will be laid consecutive by connecting them to each other at their ends by riveting 100mm steel thin plates to the vertical flanges of the consecutive main runners.

Finally, cross T-grid runners of the length 1200mm will be fixed to main runners by inserting cross runners both ends in the opening holes of main runners every 600mm.

Then the cross T-Grid runners of length 600mm will be inserted between the cross T-grid runners of length 1200mm to form a module size of 600 x 600mm as per catalogue.