Method Statement For Supply & Installation Of Cold Storage Room

Required tools & equipment’s:

Installation Of Cold Storage Room

Site Preparation

Before commencing the panel installation the following works are required to be carried out.

Mark off the location of the room on the floor from one side. For Cold room, the floor insulation can also be realized by using floor panels that are directly installed on the floor surface before installing the wall panels. The final finish of the floor would be as per the client’s requirement &  will be provided by contractor with necessary identification.

Floor angles are fitted on the base floor to the required dimensions of the cold rooms.

Generally 100 x 75mm floor angle fabricated with the same sheet as that of the panel cladding material will be fixed to the floor by Hilti nail, to the required dimensions of the cold rooms.

Wall panels are installed on the fixed floor angles.

Ceiling panels are installed to rest on the top edges of the wall panels.

Door Installation:

Fixing of lights.

Fixing of Pressure Release Valves.

  1. Pressure Release valves are installed on the wall panels above the door openings in order to equalize the pressures of the room and the ambient condition.
  2. Pipe insulations can be cladded with foster cloth.
  3. Power Consumption = 11 kw, 3phase, 50 htz, 380 to 400 volts.

INSTALLATION PROCEDURE FOR REFRIGERATION SYSTEM:

  1. Evaporator is installed as per approved drawing inside the chiller room at the ceiling level to ensure uniform, air-circulation.
  2. Condensing units for all cooling are installed as per approved drawing on the steel structure outside the cold room.
  3. The units are interconnected with copper pipes for suction, liquid and discharge line layout with necessary bends and fixtures.
  4. Evaporator and condensing units are inter-connected as shown in the basic refrigeration system diagram with necessary electrical wiring including the controls.
  5. Evaporator condensate will be connected to the nearest drain point.
  6. From the heat exchanger liquid line is connected to expansion valves through solenoid valve and suction line is connected to evaporator outlet.
  7. Filter dryer’s sight glass, shut off valve fixed on the foundation of condensing unit placed on GI frame and connected to the refrigeration circuit.
  8. After the completion of piping work, flush the system with nitrogen gas and allow passing nitrogen gas for checking the leakage of the system.
  9. Vacuum the entire system for 24 hrs by vacuum pump and then fill the system with approved refrigerant.
  10. The electrical control panel & display unit will be fixed in the cold room at desired height and location suitable for easy operation as per approved drawing.
  11. The control panel is designed for easy auto operation till the required temperature is obtained and it set to the temp differential ‘20 C’ so the system will maintain the required temperature.
  12. Finally units are commissioned and checked to obtain the required temp in the cold room. To prevent floor cracks during initial commissioning, the room temperatures to be reduced in 30 C
  13. For Refrigeration system designed with air cooled condensing units. All the other fixtures remain the same.