Site icon Project Management 123

Land Surveying Method Statement for Projects

Land Surveying Method for construction and road projects

The purpose of Survey work will include, but not be limited, to the following;

The scope of this method statement is for the land survey works of the company projects.

Related References

Project Technical Specification .

PERMANENT MARKS At least 4 permanent survey marks will be established around the project in secure locations. The horizontal and vertical relationship of these marks will be determined to a relative accuracy of:

Horizontal     ± 3mm

Vertical         ± 2mm

In the event that any mark is disturbed it can be re-established or its position re- measured from the adjoining marks.

This surveying method statement should be read in conjunction with the below referenced project documentations.

Roles & Responsibilities

The Construction Manager is over all responsible for the implementation of method statement and ensures that his team of Engineers, surveyor and foreman are aware of this method statement and the all resources – human, material and equipment’s are available to carry out the work as planned and without any delay.

The Project Engineer is responsible to carry out the work as per the approved shop drawings, method statements, contract spec. and documents. He is also responsible to ensure adequate equipment’s for concreting; finishing and curing materials are in place before concreting.

Construction Manager is responsible to plan the schedule of as-built surveys, identify non-conforming i.e. out of tolerance structures and issue the report to QA/QC department.

Surveyors are responsible for all the setting out done on site, As– built surveys and the details given for submission.

The Safety Engineer is responsible to ensure that all Safety precautions are in place, and that all personal on site are using the required Personal Protective Equipment’s like – Helmet, Gloves, Shoes, and coveralls.

All personnel will be trained, prior to start the site surveying work related HSE / Quality Control / Method statement.

Site working hours shall be as per company policy. However, if work demands survey work can be commenced in evening or night based upon site conditions (lighting arrangement, etc. shall be necessary).

Safety Engineer shall ensure to maintain safety for all aspects.

Safety assistant are allocated at all the site locations to maintain housekeeping.

Manpower, Material and Equipment Requirements

Manpower

Material requirements

Equipment requirement

The following are the major items of survey equipment that will be used:

SURVEYING PROCEDURE / METHOD TO EMPLOY

Survey control

Raft Foundation to 00 Grade parking

For the excavation, raft foundation and initial levels of construction, position and height will be established by direct measurement from the permanent marks and temporary control points established at each level. As soon as the slab is completed at each level then the permanent grid points and grid lines will be set out.

Grade parking to Level 10

Vertical Control

Transfer of datum

Line and level datum will be progressively transference up the building at every 10–12 floors and survey points closed off behind.

As built surveys

As built surveys will be carried out as follows:

    • Lift shaft surveys
    • Core Wall verticality surveys
    • Column and shear wall position & verticality
    • Precast setting out / Edge of slab surveys
    • Slab level surveys

On site survey procedures

Primary survey control

The 4 permanent marks established surrounding the site are considered to be the Primary points and all precise work must be connected to these marks by closed traverse and/or level run.

Secondary control

Marks established by closed traverse and/or level run within or adjoining the structure are considered secondary control and are used to establish control at all other levels of the building.  The traverse or level run miss-close must always be adjusted before the secondary marks are used for the set out of further points.

Horizontal Position

Vertical Position

Core wall control

Column control

Three offset points or two lines are to be marked on the current slab defining the base of the column.

Slab edge

Survey points set out on the slab below each span are plumbed to the next level to control the edge of slab form. Grid lines shall be established top of the slab prior to casting and edges shall be marked and confirmed by representative of precast company. Once slab been cast all grid lines to be marked by surveyor.

Accuracy

At all times the aim is to achieve an accuracy of 5mm in relation to the secondary survey control in setting the formwork at any one level.  This applies to both horizontal and vertical position.

Instrument calibration

SURVEY PROGRAM – KEY TASKS

HEALTH, SAFETY AND ENVIRONMENT

Survey staff will comply with all on-site safety procedures as set out and updated from time to time.

In addition the following items have been identified as job specific potential hazards for the survey team:

Exit mobile version