Site icon Project Management 123

METHOD STATEMENT FOR INSTALLATION OF LV SWITCHBOARDS, MCCs, CAPACITOR BANKS, VFDs, SMDBs AND DISTRIBUTION BOARDS

The purpose of this Method Statement is to establish a systematic procedure for the safe handling, installation, inspection, testing, and commissioning of Low Voltage (LV) Switchboards, Motor Control Centers (MCCs), Capacitor Banks, Variable Frequency Drives (VFDs), Sub Main Distribution Boards (SMDBs), and Distribution Boards (DBs).

This document ensures that all installation activities are executed in accordance with approved shop drawings, project specifications, manufacturer recommendations, local authority regulations, and applicable international standards while maintaining the highest levels of quality and safety.

This method statement covers all activities associated with the receipt, storage, handling, installation, cable termination, earthing, inspection, testing, and pre-commissioning of:

The procedure applies to all electrical rooms, plant rooms, utility areas, substations, and associated locations within the project.

REFERENCES

The installation shall be carried out in accordance with the latest editions of:

ROLES AND RESPONSIBILITIES

Project Manager

Electrical Site Engineer

QA/QC Engineer

HSE Officer

Electrical Supervisors / Foremen

Electricians and Technicians

TOOLS AND EQUIPMENT

The following tools and equipment shall be available and maintained in good working condition:

MATERIALS

LV Switchboards, MCC’s, Capacitor Banks, VFD’s, SMDB’s & DB’s and accessories shall be in line with the approved material submittal and approved drawing by local authority as per rules and standard. All materials shall be approved prior to installation and shall include:

All materials shall comply with approved material submittals and project specifications.

HANDLING AND STORAGE

On receipt of the LV Switchboards, MCC’s, Capacitor Banks, VFD’s, SMDB’s & DB’s and accessories at site, necessary precautions shall be taken for unloading, shifting & storage, as follows:-

Material shall be stored in a covered / dry space at all the time.

All materials received at site shall be inspected and ensured that the materials are as per approved material submittal.

Any discrepancies, damage etc., found will be notified and reported for further action suitably and in case if the repairs could not be done properly, the panel boards are to be sent to assembler for rectification, after all formalities carried on.

Delivery Inspection

Upon arrival at site:

Storage Requirements

Damage Control

Any damaged equipment shall be:

PRE-INSTALLATION REQUIREMENTS

Ensure that the work area is ready and safe to start the installation of LV Switchboards, MCC’s, Capacitor Banks, VFD’s, SMDB’s & DB’s.

Make sure that installation of LV Switchboards, MCC’s, Capacitor Banks, VFD’s, SMDB’s & DB’s are carried out in accordance with manufacturer’s installation recommendations, requirement of applicable standards and in accordance with recognized industrial practices and specified in project specification to ensure that installation complies with requirements.

Prior to start the installation, refer to the approved shop drawings related to the area of installation and ensure that required materials are available at site as per approved material submittals.

Ensure the materials were stored properly and there is no mark of damage or deformity of any kind before issuing the material from site store. All materials and accessories should also be free of dust, scale, or oil.

Ensure that the issued materials are of approved specifications / submittals and as per the the requirement of the area shop drawing’s. (i.e. Make, size, Model / Type etc.,).

Before commencing installation, ensure:

INSTALLATION PROCEDURE FOR LV SWITCHBOARDS, MCCs, CAPACITOR BANKS AND VFDs

Ensure the floor surface is ready with base frames grouted to install the switch gear. Minimum clearance of 750 mm (as per regulation) shall be maintained at rear side of the panel so that easy access for termination of cables and other maintenance works can be carried out.

Switchboards shall be installed serially and with Level Verticality in accordance with the Manufacturer’s recommendations, approved site layout and as per site requirement.

Check cabinet interconnections, bus bar connections, control wire connections between the cubicles after proper alignment of the sections cubical as per manufacturer’s drawing and approved shop drawing.

All knockouts made on the panel covers shall be filed and provided with grommets to avoid sharp edges and unused knockouts shall be covered.

Connection of Bus bar Trunking with all panel boards shall be done rigidly with proper supports.

Cables bending radius should not be less than the 8 times of the Cable diameter in line with the Manufacturer’s recommendation.

Appropriate tools & tackles such as Rollers, Pull Cords etc., to be utilized, while cable pulling operations including Pulling winch for longer lengths.

Termination of Cables shall be done using approved cable glands and lugs.

Cable glanding and connections should be done only by competent technicians / electricians.

All panel boards and switchgears shall be provided with proper earthing connections as per approved shop drawings.

Complete wiring & terminations related to BMS shall be provided as per approved shop drawings.

Manufacturer recommendations are to be followed for all relay, timer and other breaker current settings, as per the total connected loads and the discrimination study of the system.

Identification labels of approved type shall be fixed on all panel boards.

Co-ordinate with the Main Contractor and ensure provision of Chequer plates on the open trenches inside the LV Room & Electrical rooms.

Ensure that all Cable entries and other openings of Electrical / LV Room, Wall / Floor are sealed with proper approved sealant.

Manufacture representative to verify the Site installations and provide acceptance of same prior to Energization of Panel boards after obtaining clearance from Site Engineer

Positioning and Placement

Alignment and Leveling

Assembly of Multi-Section Panels

Where panels are supplied in multiple sections:

Working Clearances

Maintain minimum operational and maintenance clearances in accordance with:

Recommended minimum rear clearance: 750 mm unless otherwise specified.

Cable Entry Preparation

Busbar Trunking Connection

Where applicable:

Cable Installation and Termination

Earthing

Provide earthing connections to:

All earth connections shall be installed as per approved earthing drawings.

Control Wiring and BMS Interface

Equipment Identification

Install durable labels indicating:

Sealing of Openings

Seal all cable penetrations and wall/floor openings using approved fire-rated sealants to maintain fire compartment integrity.

INSTALLATION PROCEDURE FOR SMDBs AND DISTRIBUTION BOARDS

Installation works shall be carried out only in Accordance to approved shop drawings of latest revision.

Make sure that all civil & finishing works are completed and area is released for the area of installation and cleared by civil section to proceed on with Distribution board installations. Also ensure that the work area is clean and safe to take up activities.

Ensure the floor/ wall surface is ready to install the Distribution Boards.

Clearances are to be maintained between the SMDB’s and between the DB’s, as specified in the approved shop drawings.

Height of the Distribution Boards shall be maintained as per approved shop drawings so that easy access for termination of cables and other maintenance works can be carried out.

Connection of cable trays with all Distribution Boards shall be done rigidly with proper supports.

All knockouts made on the panel covers shall be filed and provided with grommets to avoid sharp edges and unused knockouts shall be covered. All cable entries shall be closed and sealed in a proper way.

Termination of cables shall be done using approved cable glands and lugs Glanding and connections should be done by only competent technicians electricians as per the approved
shop drawing.

All SMDB’s, DB’s shall be provided with proper earthing connections as per approved shop drawings.

Doors of all SMDB’s, DB’s are to be earthed with flexible connection.

Identification labels of approved type shall be fixed on all SMDB’s, DB’s.

Mounting

Alignment

Cable Connections

Cable Entry Protection

Earthing

Circuit Identification

Install approved circuit directories and identification labels for all outgoing circuits.

QUALITY CONTROL REQUIREMENTS

The following checks shall be carried out:

All inspections shall be recorded on approved inspection forms.

TESTING AND PRE-COMMISSIONING

Prior to energization, perform:

Visual Inspection

Electrical Testing

Manufacturer Inspection

Where required, the manufacturer’s representative shall inspect and certify the installation prior to energization.

HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS

ATTACHMENTS

  1. Risk Assessment
  2. Inspection and Test Plan (ITP)
  3. Material Inspection Report
  4. Installation Checklist
  5. Cable Termination Checklist
  6. Earthing Checklist
  7. Pre-Commissioning Checklist
  8. Manufacturer Test Certificates
  9. Quality Control Procedure
  10. Inspection Request Forms
Exit mobile version