Author Archives: Web Master

Method Statement For Roof Waterproofing System

Following equipment and tools will be used as required during Roof Waterproofing System. Wire Brushes Soft Brushes Air Compressor Paint Brushes Paint rollers Scissors / Cutters Torch with Gas Cylinders etc. Wheel barrow Spatula Other Hand Tools etc. PROCEDURE FOR WATER PROOFING: STORAGE AND HANDLING OF MATERIALS: Materials shall be stored in a cool and… Read More: Method Statement For Roof Waterproofing System »

Superstructure Concrete Method Statement

Below is a precise method statement for superstructure concrete works which is applicable for any kind of the project. Setting out: Prior to the commencement of the works, confirm and establish all reference points and levels. Locate, confirm and protect control points prior to starting the site concrete works. Formwork Requirements Make sure that the formworks… Read More: Superstructure Concrete Method Statement »

Dewatering System Installation & Operation Method Statement

Dewatering is defined as the removal of the ground water to a level below the normal water table, to enable excavation and construction to be carried out in suitable and safe working condition. It is proposed to install a single-stage well point system and sump pumps to control the ground water within each excavation area.… Read More: Dewatering System Installation & Operation Method Statement »

Method Statement for Underground Cable Laying

This electrical safework method statement describes the management arrangements and system of work to adopted for the laying cable for the electrical project. Below is necessary tools & equipment for performing the site activities for laying the cable. Cable Rollers Cable Pulling Grip Hand Cable cutter Manual Cable Crimpers Hydraulic Pole Saws Hand shovel Pickaxe… Read More: Method Statement for Underground Cable Laying »

Co2 Fire Suppression System Installation Method Statement

This Work Method Statement (WMS) is to describe the method for the CO2 fire suppression system installation & pressure testing for any kind of a project. The aim and /or benefit of complying with this method of statement includes the project specifications & program compliance, Health, Safety, Quality and Environmental company policy compliance. All installation… Read More: Co2 Fire Suppression System Installation Method Statement »

Project Close Out Report / Checklist – Template

Were the project objectives (expected outcomes) Accomplished? Explanation if required Were all Deliverable submitted and accepted? Explanation if required Did the Client/Engineer verify that all deliverable met the requirements? Explanation if required Have all subcontracts been closed? Explanation if required Have all final payments been made? (i.e., invoices paid) Explanation if required Have all the project resources been relocated? Explanation if required Have… Read More: Project Close Out Report / Checklist – Template »