Construction Company Transport & Green Travel Policy – Example

Below is an example of transport and green travel policy which can be useful for different type of companies and contractors. By implementing this transport policy is an organization can reduce environmental impacts and improve performance by minimizing noise, disruption and congestion to others. Objective of the policy also is to minimize pollution and improve… Read More: Construction Company Transport & Green Travel Policy – Example »

Road and Transport Works Terms & Definitions

Below are terms, words or expressions used in road works specifications tenders, communications and other project documents. These shall have the meanings hereby assigned to them. Aggregate: Hard mineral elements of construction material mixtures, for example: sand, gravel (crushed or uncrushed) or crushed rock. Anchorage: Anchorage is the device comprising all the components and materials… Read More: Road and Transport Works Terms & Definitions »

Method Statement For Roof Waterproofing System

Following equipment and tools will be used as required during Roof Waterproofing System. Wire Brushes Soft Brushes Air Compressor Paint Brushes Paint rollers Scissors / Cutters Torch with Gas Cylinders etc. Wheel barrow Spatula Other Hand Tools etc. PROCEDURE FOR WATER PROOFING: STORAGE AND HANDLING OF MATERIALS: Materials shall be stored in a cool and… Read More: Method Statement For Roof Waterproofing System »

Superstructure Concrete Method Statement

Below is a precise method statement for superstructure concrete works which is applicable for any kind of the project. Setting out: Prior to the commencement of the works, confirm and establish all reference points and levels. Locate, confirm and protect control points prior to starting the site concrete works. Formwork Requirements Make sure that the formworks… Read More: Superstructure Concrete Method Statement »

Dewatering System Installation & Operation Method Statement

Dewatering is defined as the removal of the ground water to a level below the normal water table, to enable excavation and construction to be carried out in suitable and safe working condition. It is proposed to install a single-stage well point system and sump pumps to control the ground water within each excavation area.… Read More: Dewatering System Installation & Operation Method Statement »

Method Statement for Underground Cable Laying

This electrical safework method statement describes the management arrangements and system of work to adopted for the laying cable for the electrical project. Below is necessary tools & equipment for performing the site activities for laying the cable. Cable Rollers Cable Pulling Grip Hand Cable cutter Manual Cable Crimpers Hydraulic Pole Saws Hand shovel Pickaxe… Read More: Method Statement for Underground Cable Laying »