Category Archives: Civil Method Statements

Method Statement For Removal & Transportation Of Struts

Following tools or equipment shall be arranged before starting the work. Crane – 200 to 300T : 1 No. Tower cranes at site Flat bed trailer : 1 No. Scaffolding (with green tag) Gas Cutting sets : 2 Nos. Welding set : 2 Nos. Lifting gear as required The following procedure describes the major tasks… Read More: Method Statement For Removal & Transportation Of Struts »

Method Statement for Installation of Stone Cladding Works

The following equipment and tools shall be provided with the necessary numbers to suit the numbers of skilled fixers: Leveling Instruments Masonry Tools Brushes Rubber Mallets Spirit Levels Adjustable Wrenches Open Wrenches Stone Steel Holders Spatulas Aluminum Straight Edge Measurement Tapes Stone Cutting Machine/Power Saw Plumb Line and Plastic Strings Steel Hammers Masking Tapes, etc.… Read More: Method Statement for Installation of Stone Cladding Works »

Method Statement For Painting Works

All painting works shall be carried out strictly in accordance with approved paint manufacturer’s recommendations and relevant applicable standards. Application of Painting system to the internal/external surfaces shall be as approved by the CONSULTANT and as required in compliance with manufacturer’s recommendations, approved method statement, drawings and project specifications. Before commencing the painting works, subsequent… Read More: Method Statement For Painting Works »

Method Statement For The Installation Of EOT And Monorails Crane Anchor & Runway Beams

Lifting Equipment: Chain block / Lever Block used to lifting the beams at the installation area. Usually use to help workers to lift the beams at low level height before fixing the connection bolts the same also for aligning the connection of the beams. Rotating & Power Machines: Welding Machines (if required at site during installation –… Read More: Method Statement For The Installation Of EOT And Monorails Crane… »

Laying of Dense Bituminous Macadam DBM – Road Construction

This method statement covers the laying of Dense Bituminous Macadam (DBM) in 50 to 100 mm thick layers as profile correction course (PCC) on a previously prepared existing concrete surface as per specified lines & grades. The road construction works shall comply the contract agreement, project specifications, relevant drawings and applicable local and international standards.… Read More: Laying of Dense Bituminous Macadam DBM – Road Construction »

Road Maintenance Method Statement Including Cracks Potholes Patches Edge Breaks

Contractor will carry out the road maintenance and construction works in compliance with the technical specification and engineer’s instructions. With the direction and instruction of the client/ consulting engineer, at the designated areas, the motor graders and excavators are used to clear, remove, and dispose all vegetation, silt and grubbing roots, down timber and other… Read More: Road Maintenance Method Statement Including Cracks Potholes Patches Edge Breaks »