Lighting Control System Installation Method Statement

By | June 16, 2026

Below method statement defines step by step procedure for lighting control system installation. By following this electrical methodology the installer shall make sure that the installation job execution complies with the project requirements and serves the intended function to the satisfaction of the client/consultant.

This method statement refers to various work procedures contained within project control documents, which explains and covers the installation of lighting control system.

Overall project manager is responsible for site works in coordination with project electrical engineer and his team, including QA/QC and HSE.

Lighting control system components and accessories shall be in line with the approved material submittals, approved drawings, specifications and applicable standards.

Before start of work arrange below tools & equipment:

  • Standard electrician & wireman tools
  • Portable hand tools
  • Spirit Level / Level Threads
  • Digital multimeter

MATERIAL HANDLING & STORAGE

On receipt of the Lighting Control System accessories at site, necessary precautions shall be taken for unloading, shifting & storage, as follows:

All Packages for the complete set of Lighting Control System, reaching to site shall be identified as per package list.

Where auxiliaries are shipped loose, these will be identified and checked against the dispatch documents.

Any item found missing or damaged will be notified to the supplier immediately for the replacement / repair.

All materials received at site shall be inspected and ensured that the materials are as per approved material submittal, shop drawing and single line diagram.

 Any discrepancies / damage found will be notified and reported for further action.

Site engineer will ensure that material used at site are free from any defect/damage.

All packages shall be stored under protected area from dust, dirt and moisture.

PRE INSTALLATION PROCEDURE FOR LIGHTING CONTROL SYSTEM

Ensure all civil works are completed for the area to carryout the installation, and clearance is obtained from respective authorities to proceed further.

Prior to start the installation, refer to the approved shop drawings related to the area of installation and ensure that required materials are available at site as per approved material submittals.

Before the installation of lighting control system make sure materials were stored properly and there is no mark of damage or deformity of any kind.

All shop drawings, riser diagrams, installation methods and details must be approved by consultant.

Lighting Control System Installation Method Statement

Ensure that all outlets related to Lighting Control System are in accessible area and not covered by MEP services.

Ensure that work area is ready and safe to start the installation of Lighting Control Systems.

Site engineer shall overall ensure that the installation of Lighting Control System and accessories are carried out in accordance with manufacturers installation recommendations, requirements of applicable standards and in accordance with recognized industrial practices, and also as specified in project specification to ensure that installation complies with all requirements.

After LCS installation and prior to start the false ceiling work consultant comments if any shall be finished/approved.

LIGHTING CONTROL SYSTEM INSTALLATION

The installation of lighting control consists of the following steps:

1) Conduiting and Cabling
2) Switch Actuator panel/Lighting control panel
3) EIB Power Supply / Line Coupler
4) Universal Interface / Switch Sensors

Conduiting and Cabling

PVC conduiting / GI conduiting or trunking shall be done as per approved shop drawing to pull EIB & Bus Cable for all field devices and control panels. This is already installed and approved by consultant by using the inspection requests.

Switch Actuator / Lighting Control Panel Installation

These shall be mounted in purpose made enclosure and adjacent to lighting distribution board in the electrical room.

Power Cables from the lighting DB shall be terminated at the incomming terminal with proper care.

Outgoing circuits to light fittings shall be terminated at the outgoing terminal of the switch actuator.

Physical address for each actuator panel shall be written in front and in bold letters.

EIB Power Supply & Line Coupler Installation

Power Supply unit & Line Coupler shall be mounted in the same enclosures of actuators or in separate enclosures as per lighting control system manufactures design drawings.

The auxiliary voltage may not be used for other purpose than Bus.

Mains Supply shall be connected at Terminal L1, N.

Main shall be switched on, once the device has been correctly installed.

Universal Interface Installation

Interface shall be Installed in 3×3 back box.

EIB Bus cable shall be terminated at Bus terminal with correct polarity.

Wires which are not required should be insulated.

Physical address shall be written on each module once they are programmed.

Brightness Sensor Mounting

The lighting brightness sensor is fixed with a mounting bracket.

Maximum cable length should not exceed 100 meter.

Light sensor should not be installed in shadow.

If light sensor is used for external lighting it should face Eastwards/Westwards.

If light sensor is used for room lighting it should face Northwards/Southwards.

After the completion of installation of Lighting Control System, an inspection request shall be raised for consultant approval.

ATTACHMENTS

Inspection and Testing Plan ITP

Inspection Checklist

Quality Control Procedure

Risk Assessment


Discover more from Project Management 123

Subscribe to get the latest posts sent to your email.