Method Statement for Tiling Work Installation of Ceramic, Porcelain & Agglomerate Tiles

Below is step wise civil work method statement for tile fixing and installation of ceramic, porcelain & agglomerate tiling works for any kind of building projects.

Following is list of necessary equipment’s and tools that are mandatory for the tiling work:

  • Drum mixer
  • Grinder/saw or wet diamond table masonry cutter
  • Aluminum straight edge
  • Trowel
  • Plumb
  • Spirit level
  • Wheel barrow
  • Hand Shovel
  • Water tank
  • Right Angle
  • Rubber mallet and other Hand tools as required.

Procedure of Tiling Work Installation

Material Delivery, Storage and Handling:

Only best quality and approved materials will be used in execution of tiling works.

Handling, delivery and storage of tiles, adhesives and cementitious / grout materials will be in a manner to ensure no discoloration and damages occurs.

Tile consignments shall be stacked in batches segregated with respect to type, color, shape, thickness and form.

The tiles from different batches will not be mixed in one batch / bundle.

Coordination, Inspection and Preparatory Works:

MEP clearances will be taken from the MEP subcontractor to start the tiling work.

Provision of floor drains, where applicable, will be ensured as per approved shop drawings.

Base work to receive tiles will be examined prior commencing fixing and installation of tile works and discrepancies regarding accuracy and suitability in location that may adversely affect installation and permanency of works, if any found, will be reported to consultant and necessary needs to be fulfilled.

Before laying tiles it will be ensured that relevant setting out and shop drawings are approved by client/consultant.

Make sure that there are no unintended color/shade variations within the tiles for use in each area and tiles delivered at site are as per approved dimensions and relevant approved material approval requests.

Variegated tiles, where found unavoidable, will be thoroughly mixed to ensure symmetrical and uniform appearance of completed tile works.

Tile Fixing Work Mockup Preparation

Mock-ups for each type on consultant identified location will be installed for Consultant’s approval, prior to start tiles installation construction of actual works accordingly.

Actual works will be carried out in accordance with consultant approved mock-up.

Approved mock up may remain as part of the completed works.

Substrate Preparation of floors:

Cast in place concrete substrate shall be sufficiently smooth and level so that thin set mortar/adhesive to accept tiles is easily and smoothly applied.

Grind off high spots and fill in low spots as necessary to ensure no void occurs.Safe Method Statement for installation of Ceramic Floor Tiles

All toilets and pantries where waterproofing is mandatory, apply waterproofing prior to installation of tiles following the detail as shown on the relevant approved drawings, and as per the approved waterproofing procedure.

Substrate Preparation of walls:

Where the walls are to be finished with tiles, apply a leveling coat of cement mortar as approved to a minimum thickness of 12mm, sufficient to cover the unevenness of the substrate and to make walls true vertical.

Mortar will be trowel smooth to leave a surface suitable for use of tile adhesive as approved.

Where shown on the drawings, apply the waterproofing using the materials as approved in accordance with manufacturer’s recommendations prior to installation of tiles on walls.

Setting out and Installation of Tiling Work

Mix bedding / adhesive materials thoroughly as approved to a uniform consistency in a suitable forced action as per manufacturer’s recommendations.

For installation of ceramic/porcelain/agglomerate tiles check all installation details as required by approved shop drawings/finishing schedule etc.

Only approved tile adhesive /mortars will be applied to substrate and backside of the tiles as per the manufacturer’s recommendations.

The laying and fixing of tiles will start from the location marked on the approved shop drawing and mentioned as “Start Point.”

Tiles will be laid in prepared area to give true and regular appearance to tiles and joints maintaining the desired level as shown on the approved drawings.

The tiles will be fixed in accordance with approved setting out drawings.

Level marks will be provided and set out up to finish level as per surveyor’s marking based on the approved drawings.

Tiles will be fixed in place and pressed firmly with twisting / sliding action to give finished bed thickness within the tolerance limits as defined in specifications and drawings.

Installation will be in a manner to ensure that no voids under the tiles occur.

It will be ensured that tile joints are true to line, continuous and without steps.

The joint width will be 2mm or shall be determined according to manufacturer’s recommendations and the material used for grouting.

Ensure that all the joints in skirting and joints between walls and floors are continuous and match in alignment.

Supply and laying, fixing or installation of the various types of floor and skirting finishes will be as shown on the approved shop drawings or finishing schedules.

The materials used for each type of floor and skirting finishes shall be approved by the consultant.

Control joints will be provided in large areas in each direction and at perimeter walls or where required as per detail shown in relevant approved shop drawings.

The tiles will be fixed closely to electrical outlets, piping, fixtures, and other penetrations so plates, collars, or covers overlap the tile.

Tile fixing work will be extended into recesses and under or behind equipment and fixtures to form a complete covering without interruptions, unless otherwise indicated and will be terminated neatly at obstructions, edges, and corners without disrupting pattern or joint alignments.

Pre-mould corner pieces shall be provided for all right angle corners as per approved shop drawing.

Surfaces will be sloped uniformly where indicated/required by drawings.

Tile floors shall be finished flush with gratings, strainers and drains, where applicable and as shown on the drawings.

Grouting Requirements

Application of tile adhesives and grouts, as approved, will be carried out in accordance with manufacturer’s recommendations and relevant temperature and humidity conditions specified in manufacturer’s product data sheet.

Allow bedding/adhesive materials to harden sufficiently before grouting.

Ensure that the joint width and depth is maintained to 2mm & 6mm (or the depth of the tile if less) respectively or in accordance with grout/tile manufacturer’s recommendations and free from dust and debris.

Grouting and filling of joints will be done in accordance with grout manufacturer’s recommendations.

Grout will be forced to fill joints completely to entire depth, tooled to an approved profile, clean off by leaving surfaces free from blemishes.

Control Joints / Expansion Joints will be provided as per approved shop drawings and will be sealed with approved special sealants.

Floor will be closed for all kind of traffic including foot traffic for 24 hours (or as per manufacturer’s recommendations) after installation for sufficient hardening.

Wall Tile Installation Method

Installation of all types of tile designated for wall installations to comply with requirements in the schedule.

The joint width for tiles on walls will be 3mm or according to approved shop drawing.

Agglomerate Tiling works

The installation of agglomerate tiles at the locations shown on the approved shop drawings, shall be done using only the approved materials and in accordance with manufacturer’s recommendations.

Manufacturer’s instruction shall be followed for mixing of adhesive cement as approved.

When fitting the agglomerate tiles, the humidity level in the surface is recommended to be less than 2% as per manufacturer’s instructions.

The tiles and floor must be clean, dry and dust free.

Flatness of the surface should not have any variation over 3mm when measured with a 2m level.

Floor will be leveled off when required using the leveling paste as per manufacturer’s recommendations up to an approximate thickness of 10mm.

Place the adhesive cement on the reverse side of the tile using 6-8mm grooved trowel as per manufacturer’s instructions.

Now place the tile one by one, leaving the expansion joints every 40m² or as per detail shown on the approved shop drawings.

Joints width will be maintained at least 3mm between tiles and 5mm at perimeter expansion joint or as per approved shop drawings.

In the event of fixing the tiles outdoors, the minimum gap between tiles shall be 5mm and the partition joints shall be made every 30m² or as per detail shown on the approved shop drawings.

When the tiles used are more than the standard size, the joint width will be increased in proportion to the size of the tiles.

After placing, ram the tile to its position using rubber mallet until they are fully adhered to 100% of the adhesive mortar.

Clean the mortar / material that oozes out of the joints/gaps using a moist mop before application of the grout.

Grouting and filling of joints will be done in accordance with grout manufacturer’s recommendations after adhesive mortars harden sufficiently i.e. 24-48 hours.

Any remains of the tile grout will be cleaned immediately after completion of works.

Cleaning/Finishing and Protection of Tiling Work

Installed tiling works will be kept cleaned and protected as work progresses.

After grouting and pointing, tiles will be cleaned with stiff fiber brushes and water. The use of wire brushes or acids shall not be permitted.

Mortars/excessive grouts and alkali washed-offs if any, will be removed from surfaces.

At completion, flush down with water to make surface good and cleaned.

All debris, equipment and excess material resulting from the tile fixing work will be removed from the site upon completion of tiling works in the area.

Two coats of sealer finish will be applied to flooring and stairs, if applicable, following the sealer finish manufacturer’s printed instructions as approved.

The tiles shall be protected and maintained after completion, in a manner acceptable to the consultant/client that ensures tiles are not damaged during any other project activities.

If recommended by the manufacturer a heavy protective covering shall be provided during construction period to prevent staining and damage.

All types of foot and wheel traffic will be prohibited on the tiled floors for at least 7 days after grouting.

error: Content is protected !!