Below is a precise method statement for concrete works for vertical elements (Retaining Wall, Shear Walls, Columns etc.) Following equipment shall be arranged before starting the concrete pouring work: Survey Instruments Tower/Mobile Crane Mechanical Vibrators / Internal Vibrators Concrete Pumps Transit Mixer
Read More
Following equipment and tools will be used as required during Roof Waterproofing System. Wire Brushes Soft Brushes Air Compressor Paint Brushes Paint rollers Scissors / Cutters Torch with Gas Cylinders etc. Wheel barrow Spatula Other Hand Tools etc. PROCEDURE FOR WATER PROOFING:
Read More
Below is a precise method statement for superstructure concrete works which is applicable for any kind of the project. Setting out: Prior to the commencement of the works, confirm and establish all reference points and levels. Locate, confirm and protect control points prior
Read More
Dewatering is defined as the removal of the ground water to a level below the normal water table, to enable excavation and construction to be carried out in suitable and safe working condition. It is proposed to install a single-stage well point
Read More
The following equipment and tools shall be provided with the necessary numbers to suit the numbers of skilled fixers: Leveling Instruments Masonry Tools Brushes Rubber Mallets Spirit Levels Spatulas Aluminum Straight Edge Measurement Tapes Stone Cutting Machine/Power Saw Plumb Line and Plastic
Read More
REQUIRED EQUIPMENT / MACHINERY: Hydraulic Power Pack, HILTI DLP 30 : 2 Nos. Hydraulic Saw Head, HILTI DSTS 30 : 2 Nos. Hydraulic Hoses (set of 6 hoses) : 2 Nos. Remote Control : 2 Nos. Coring Machines HILTI DD250 : 2
Read More